Questions for the CIS-SPM were updated on : Dec 01 ,2025
Page 1 out of 8. Viewing questions 1-15 out of 112
Question 1
The Project Management application enables users to create parent-child relationships between tasks and dependencies, such as finish-to-start and finish-to-finish, between tasks. How many relationships can exist between two tasks?
A. One
B. Two
C. Three.
D. Four.
Answer:
D
User Votes:
A
50%
B
50%
C
50%
D
50%
Discussions
0/ 1000
Question 2
A customer needs to know what activity type is associated to time entries in the project so that they can capitalize build tasks. What is the best method to do this?
A. Create a capital project task flag.
B. Put all capital project tasks in one phase and report from those tasks.
C. Create an incident.
D. Leverage project time categories to classify the time.
Answer:
D
User Votes:
A
50%
B
50%
C
50%
D
50%
Discussions
0/ 1000
Question 3
Where can custom risk ranks and value scores (such as High-Medium, Medium-Low, or Absolute- Low) be configured to evaluate the impact and probability of a risk?
A. Using normalized value
B. The Risk Value Lookup module
C. Manual input
D. on the Risk form
Answer:
B
User Votes:
A
50%
B
50%
C
50%
D
50%
Discussions
0/ 1000
Question 4
How can cost plans be generated from resource assignments? Choose 2 answers
A. Select the 'Generate labor costs' button on Project Workspace
B. Update the appropriate Resource Management property
C. Run a scheduled job to automatically generate labor costs from resource assignments
D. Select the 'Generate cost' button in Resource Management Workspace
Answer:
A, C
User Votes:
A
50%
B
50%
C
50%
D
50%
Discussions
0/ 1000
Question 5
Where can a project manager go to view quick reports of time card exceptions, and category wise time reported for their projects?
A. User metrics dashboard
B. PMO dashboard
C. Analytics Project manager
D. Analytics Time sheet
Answer:
B
User Votes:
A
50%
B
50%
C
50%
D
50%
Discussions
0/ 1000
Question 6
What is used to generate labor cost if a project or demand does not have an associated rate model?
A. Default Resource Management Schedule
B. Project plan
C. Default labor rate
D. Time card
Answer:
C
User Votes:
A
50%
B
50%
C
50%
D
50%
Discussions
0/ 1000
Question 7
Which ServiceNow application interacts with SPM through risk assessments?
A. Field Service Management
B. Goverance Risk and Compliance
C. DevOps
D. IT Service Management
Answer:
B
User Votes:
A
50%
B
50%
C
50%
D
50%
Discussions
0/ 1000
Question 8
Who can submit Ideas?
A. Any ITIL user.
B. AnyIT user.
C. Any demand user.
D. Any user.
Answer:
D
User Votes:
A
50%
B
50%
C
50%
D
50%
Discussions
0/ 1000
Question 9
As an it_pps_admin, what can you use to detect corrupt data in a project, such as tasks with invalid parents or cyclic relations in a project?
A. Project Diagnostics.
B. Edge Encryption Diagnostics.
C. Analytics Diagnostics.
D. System Diagnostics.
Answer:
A
User Votes:
A
50%
B
50%
C
50%
D
50%
Discussions
0/ 1000
Question 10
When creating a program, which of the following cannot be part of multiple programs? Select all that apply. Choose 2 answers
A. Project.
B. Demand.
C. Portfolio.
D. Tasks.
Answer:
A, B
User Votes:
A
50%
B
50%
C
50%
D
50%
Discussions
0/ 1000
Question 11
Which of the following defines a parent-child relationship? Choose 2 answers
A. A parent-child task must finish before another begins.
B. Any number of child tasks can be nested under a parent task with or without any dependencies.
C. A parent-child relationship is not saved as a record in any table.
D. Parent-child task relationships do not have any effect on task time constraints.
Answer:
B, C
User Votes:
A
50%
B
50%
C
50%
D
50%
Discussions
0/ 1000
Question 12
Under the Preferences tab on the Demand form, you have the option to: Choose 2 answers
A. Close a demand on closure of a project
B. Add a risk score
C. close a demand on creation of a project
D. Add a financial benefit
Answer:
A, C
User Votes:
A
50%
B
50%
C
50%
D
50%
Discussions
0/ 1000
Question 13
Instead of starting from scratch, what can project managers make use of to rapidly build their project plan
A. Project Baselines
B. Planning Console
C. Project Workspace
D. Project Templates
Answer:
D
User Votes:
A
50%
B
50%
C
50%
D
50%
Discussions
0/ 1000
Question 14
Which of the following is the default schedule for the Project Management application?
A. Repeats every week on weekdays Monday through Friday from 8:00am to noon and 1:00-5:00pm.
B. Repeats every week on weekdays Monday through Friday.
C. Repeats every week on weekdays Monday through Friday from 9:00am to 5:00pm.
D. Repeats every week on weekdays Monday through Friday. Includes the child schedule U.S. Holidays.
Answer:
A
User Votes:
A
50%
B
50%
C
50%
D
50%
Discussions
0/ 1000
Question 15
Which options are available in the' Effort type' field on the Resource Assignments form, when requesting resources? Choose 3 answers