Questions for the C-TS422-2504 were updated on : Dec 01 ,2025
Page 1 out of 6. Viewing questions 1-15 out of 87
Question 1
Your company manufactures materials whose characteristics differ for each manufacturing process. Which application do you have to use in SAP S/4HANA Cloud Private Edition to be able to track use this information in all areas of logistics?
A. Process order management
B. Engineering change management
C. Quality management
D. Batch management
Answer:
D
User Votes:
A
50%
B
50%
C
50%
D
50%
Discussions
0/ 1000
Question 2
Your project uses process orders for the production of liquid chemicals. What can you define to ensure that production flow only happens in suitable physically connected tanks? Note: There are 2 correct answers to this question.
A. Resource hierarchy
B. Resource selection
C. Resource matrix
D. Resource network
Answer:
B D
User Votes:
A
50%
B
50%
C
50%
D
50%
Discussions
0/ 1000
Question 3
Your quality department detects a deviation in a raw material batch. Unfortunately this batch has already been used in production. How can you identify all affected finished goods stocks? Note: There are 2 correct answers to this question.
A. Use batch determination.
B. Use the Batch Information Cockpit.
C. Use the batch whereused list.
D. Use batch derivation.
Answer:
B C
User Votes:
A
50%
B
50%
C
50%
D
50%
Discussions
0/ 1000
Question 4
How can you support a GMP (Good Manufacturing Practice) compliant production process? Note: There are 3 correct answers to this question.
A. Digital signature
B. Approved resources
C. Recipe approval
D. GMPcompliant flag
E. Batch record
Answer:
A C E
User Votes:
A
50%
B
50%
C
50%
D
50%
E
50%
Discussions
0/ 1000
Question 5
Which time elements are relevant for lead time scheduling of a production order? Note: There are 2 correct answers to this question.
A. Opening period
B. Total replenishment lead time
C. Float after production
D. Setup time
Answer:
C D
User Votes:
A
50%
B
50%
C
50%
D
50%
Discussions
0/ 1000
Question 6
What are the options if the Dispatched operation status is set for a production order operation? Note: There are 2 correct answers to this question.
A. You can reschedule the operation using lead time scheduling.
B. You can reschedule the operation using infinite scheduling in a planning table.
C. You can reschedule the operation using finite scheduling in a planning table.
D. You can reschedule the operation in the Manage Work Center Capacity app.
Answer:
C D
User Votes:
A
50%
B
50%
C
50%
D
50%
Discussions
0/ 1000
Question 7
Which chart types does the tabular planning table for capacity planning provide in SAP S/4HANA Cloud Private Edition? Note: There are 2 correct answers to this question.
A. Order (pool) chart
B. Capacity requirements chart
C. Orders (dispatched) chart
D. Work center capacities chart
Answer:
B D
User Votes:
A
50%
B
50%
C
50%
D
50%
Discussions
0/ 1000
Question 8
You want to insert an operation at a certain time on a work center in the graphical planning table. The planning direction is forward. The desired dispatching time coincides with an operation that has previously been dispatched. How does the insertion take place?
A. The previously dispatched operation stays as is; the new operation is inserted before the dispatched operation.
B. The previously dispatched operation stays as is; the new operation is inserted after the dispatched operation.
C. The new operation is inserted at the desired time; the previously dispatched operation is moved forward.
D. The new operation is inserted at the desired time; the previously dispatched operation is moved backward.
Answer:
D
User Votes:
A
50%
B
50%
C
50%
D
50%
Discussions
0/ 1000
Question 9
What time element of midpoint scheduled operations can be reduced by reduction strategy settings while dispatching? Note: There are 2 correct answers to this question.
A. Queue time
B. Teardown time
C. Move time
D. Setup time
Answer:
A C
User Votes:
A
50%
B
50%
C
50%
D
50%
Discussions
0/ 1000
Question 10
What is a work center hierarchy?
A. A group of alternative work centers for production structured in hierarchy levels by priorities
B. A group of alternative work centers providing a cumulative available capacity for production
C. A group of work centers in a production line being used in sequence for production
D. A group of work centers in a parallel sequence that is used to split production quantities work on them in parallel
Answer:
B
User Votes:
A
50%
B
50%
C
50%
D
50%
Discussions
0/ 1000
Question 11
What could be the reason for multiple commitments where several operations have the same scheduled dates on a work center after dispatching? Note: There are 2 correct answers to this question.
A. The Finite Scheduling indicator is NOT set in the strategy profile.
B. The work center has several individual capacities.
C. Alternative work centers are fully occupied.
D. The Change Planning Direction indicator is set in the strategy profile.
Answer:
A B
User Votes:
A
50%
B
50%
C
50%
D
50%
Discussions
0/ 1000
Question 12
What information do you have to maintain to define the relationship between supply source dem source in the Kanban process? Note: There are 2 correct answers to this question.
A. Routing
B. Work Center
C. Replenishment strategy
D. Production supply area
Answer:
CD
User Votes:
A
50%
B
50%
C
50%
D
50%
Discussions
0/ 1000
Question 13
Which actions does the system perform by default when you save a confirmation for a finished product in repetitive manufacturing? Note: There are 3 correct answers to this question.
A. Post the goods receipt for the finished product.
B. Reduce run schedule quantities.
C. Post production costs to the planned order.
D. Update statistics for the Business Information Warehouse.
E. Create associated capacity requirements.
Answer:
B C E
User Votes:
A
50%
B
50%
C
50%
D
50%
E
50%
Discussions
0/ 1000
Question 14
How can you set up the supply source for the Kanban process in SAP S/4HANA Cloud Private Edition? Note: There are 3 correct answers to this question.
A. Use run schedule quantities for inhouse production.
B. Use stock transfer reservations for stock transfer.
C. Use purchase orders for external procurement.
D. Use quotations for internal external procurement.
E. Use purchasing costs for automated source prioritization.
Answer:
A B C
User Votes:
A
50%
B
50%
C
50%
D
50%
E
50%
Discussions
0/ 1000
Question 15
What does a line hierarchy in repetitive manufacturing represent?
A. A production line with more than one work center
B. A production line with an alternative sequence in the routing
C. A production line with a parallel sequence in the routing
D. A production line with prioritized alternative work centers