SAP C-S4PPM-2021 Exam Questions

Questions for the C-S4PPM-2021 were updated on : Dec 01 ,2025

Page 1 out of 6. Viewing questions 1-15 out of 82

Question 1

In SAP Enterprise Portfolio and Project Management, which objects can be used to exchange data
back and forth to other application objects? Note: There are 2 correct answers to this question

  • A. Project task and network activity
  • B. Project phase and WBS element
  • C. Portfolio item and Project System project definition
  • D. Milestone task and WBS element
Answer:

BC

User Votes:
A
50%
B
50%
C
50%
D
50%
Discussions
vote your answer:
A
B
C
D
0 / 1000

Question 2

Which of the following are valid breakdown periods for financial planning in Portfolio Management?
Note: There are 2 correct answers to this question

  • A. 10 days
  • B. 3 months
  • C. 1 year
  • D. 2 weeks
Answer:

BC

User Votes:
A
50%
B
50%
C
50%
D
50%
Discussions
vote your answer:
A
B
C
D
0 / 1000

Question 3

For which of the following object types can you define questionnaires?
NOTE: There are 2 correct answers to this question

  • A. Initiative
  • B. Bucket
  • C. Project management project
  • D. Portfolio item
Answer:

A, D

User Votes:
A
50%
B
50%
C
50%
D
50%
Discussions
vote your answer:
A
B
C
D
0 / 1000

Question 4

Where can you define the scheduling type?
NOTE: There are 3 correct answers to this question.

  • A. In customizing
  • B. ON phase level
  • C. On project definition level
  • D. On task level
Answer:

A, C

User Votes:
A
50%
B
50%
C
50%
D
50%
Discussions
vote your answer:
A
B
C
D
0 / 1000

Question 5

What are prerequisites for using cross-Application time sheet (SAP CATS) to confirm In a project
management project?
NOTE: There are 3 correct answers to this question.

  • A. Accounting integration for this project is active
  • B. The project type must allow time recording with the CATS
  • C. The role type must allow time recording with CATS
  • D. The planned efforts is on the task
Answer:

A, B

User Votes:
A
50%
B
50%
C
50%
D
50%
Discussions
vote your answer:
A
B
C
D
0 / 1000

Question 6

You want to distribute capacity requirements in a project management project?
How can you distribute the values?
NOTE: There are 3 correct answers to this question

  • A. Use a distribution function
  • B. Copy values from resource assignments
  • C. Apply a distribution rule
  • D. Update the capacity requirements from the roll-up of task requirements
  • E. Enter the vales manually
Answer:

A, D, E

User Votes:
A
50%
B
50%
C
50%
D
50%
E
50%
Discussions
vote your answer:
A
B
C
D
E
0 / 1000

Question 7

What can you use scoring models for?
NOTE: There are 2 correct answers to this question.

  • A. To derive field values of buckets
  • B. Top compare items in reviews
  • C. To compare bucket in reviews
  • D. To derive field values of items
Answer:

B, D

User Votes:
A
50%
B
50%
C
50%
D
50%
Discussions
vote your answer:
A
B
C
D
0 / 1000

Question 8

Which of the following are consequence of releasing a phase?
NOTE: There are 2 correct answers to this question

  • A. Predecessor phases are assigned the status locked
  • B. Lower-level tasks and checklist are release
  • C. Additional tasks cannot be added to the phase
  • D. The phase type is set to read-only
Answer:

B, D

User Votes:
A
50%
B
50%
C
50%
D
50%
Discussions
vote your answer:
A
B
C
D
0 / 1000

Question 9

Which objects can used to record times in Cross-Application Time Sheels (SAP Cats)?
NOTE: There are 3 correct answers to this question

  • A. Phase
  • B. Task
  • C. Role
  • D. Checklist item
Answer:

B, C

User Votes:
A
50%
B
50%
C
50%
D
50%
Discussions
vote your answer:
A
B
C
D
0 / 1000

Question 10

What do you use the check Conflict button for?
NOTE: There are 3 correct answers to this question

  • A. Adjustment of distribution of staffing
  • B. Adjustment of dates of roles
  • C. Adjustment of work according to roles assignment of a task
  • D. Adjustment of work according to resource availability
  • E. Adjustment of dates of staffing
Answer:

A, B, E

User Votes:
A
50%
B
50%
C
50%
D
50%
E
50%
Discussions
vote your answer:
A
B
C
D
E
0 / 1000

Question 11

Which of the following are search criteria In Resource Search in Project Management?
NOTE: There are 2 correct answers to this question.

  • A. Work centers
  • B. Organizational units
  • C. Qualifications
  • D. plants
Answer:

B, C

User Votes:
A
50%
B
50%
C
50%
D
50%
Discussions
vote your answer:
A
B
C
D
0 / 1000

Question 12

Which cost planning process can you use at item level?
NOTE: There are 2 correct answers to this question.

  • A. Integrated cost planning
  • B. Hierarchical cost planning
  • C. Manual cost planning
  • D. Rollup of cost planning
Answer:

A, C

User Votes:
A
50%
B
50%
C
50%
D
50%
Discussions
vote your answer:
A
B
C
D
0 / 1000

Question 13

What data can you synchronize between a portfolio item and an initiative using Decision Flow
management?

  • A. Documents
  • B. Notes
  • C. Metrics
  • D. Development Cost
Answer:

D

User Votes:
A
50%
B
50%
C
50%
D
50%
Discussions
vote your answer:
A
B
C
D
0 / 1000

Question 14

You want to configure portfolio management to use Financial planning for manual planning on the
item level.
Which of the following settings are required?
NOTE: There are 2 correct answers to this question.

  • A. Views
  • B. Cost element groups
  • C. Categories
  • D. Value types
Answer:

A, C

User Votes:
A
50%
B
50%
C
50%
D
50%
Discussions
vote your answer:
A
B
C
D
0 / 1000

Question 15

What is a prerequisite for using role charts in project management?

  • A. The demand of a role must have been updated according to tasks
  • B. A graphic profile is assigned to the role type
  • C. A graphic profile is assigned to the project type
  • D. The demand of a role must be distributed over a number of periods
Answer:

D

User Votes:
A
50%
B
50%
C
50%
D
50%
Discussions
vote your answer:
A
B
C
D
0 / 1000
To page 2