pmi PMI-RMP Exam Questions

Questions for the PMI-RMP were updated on : Dec 06 ,2025

Page 1 out of 18. Viewing questions 1-15 out of 264

Question 1

A risk manager is collaborating with project stakeholders and the project team to identify risks in a
construction project. The risk manager intends to use an approach that engages stakeholders based
on information, such as scope baseline and project estimates, while also determining risk impacts
based on this approach.
Which risk identification approach should the risk manager use to achieve this goal?

  • A. Strengths, weaknesses, opportunities, and threats (SWOT) analysis
  • B. Brainstorming technique
  • C. Delphi technique
  • D. Assumptions and constraints analysis
Answer:

D

User Votes:
A
50%
B
50%
C
50%
D
50%

Explanation:
Assumptions and constraints analysis focuses on reviewing project documents (scope baseline,
estimates, etc.) to determine what is assumed or constrained, and then assesses the risks arising
from those assumptions and constraints. The PMBOK® Guide describes:
"Assumptions and constraints analysis explores the validity of project assumptions and constraints,
as documented in scope baselines and estimates, and evaluates their potential impact on project
objectives."
— PMBOK® Guide, 6th Edition, Section 11.2.2.2
Reference:
PMBOK® Guide, 6th Edition, Section 11.2.2.2

Discussions
vote your answer:
A
B
C
D
0 / 1000

Question 2

A risk manager has been assigned to prepare a risk management plan for a new project. Which factor
should the risk manager prioritize when tailoring the risk management processes for the new
project?

  • A. Available funds for risk management activities
  • B. Size and duration of the project
  • C. Maturity of the organization's risk management processes
  • D. Number of stakeholders associated with the project
Answer:

B

User Votes:
A
50%
B
50%
C
50%
D
50%

Explanation:
Tailoring risk management processes is mainly based on the size and duration (complexity) of the
project. The PMBOK® Guide confirms:
"The size, complexity, and duration of the project are primary considerations when tailoring risk
management activities. Larger or longer projects require more rigorous processes."
— PMBOK® Guide, 6th Edition, Section 11.1
Reference:
PMBOK® Guide, 6th Edition, Section 11.1

Discussions
vote your answer:
A
B
C
D
0 / 1000

Question 3

When should the benefits of quantitative risk analysis be weighed against the effort required to
ensure that the additional insights and value justify the extra effort?

  • A. During the Plan Risk Management process
  • B. Once all individual risks have been scored
  • C. After risks have been identified by stakeholders
  • D. Once the overall project risk has been estimated
Answer:

A

User Votes:
A
50%
B
50%
C
50%
D
50%

Explanation:
The Plan Risk Management process is where the project team determines the depth and breadth of
risk management activities, including whether quantitative risk analysis is appropriate. PMBOK®
Guide says:
"The Plan Risk Management process determines how to approach and conduct the risk management
activities for a project. This includes weighing the benefits and effort of advanced techniques such as
quantitative risk analysis."
— PMBOK® Guide, 6th Edition, Section 11.1
Reference:
PMBOK® Guide, 6th Edition, Section 11.1

Discussions
vote your answer:
A
B
C
D
0 / 1000

Question 4

The risk manager for a large-scale software development project with a tight deadline and multiple
stakeholders highlights concerns about potential delays, communication gaps, and vendor reliability.
During the early stages of the project, the project sponsor requests that the risk manager identify
and address any potential risks that could disrupt project delivery.
What should the risk manager do?

  • A. Create a list of potential issues.
  • B. Consult the project management plan.
  • C. Conduct risk management exercises.
  • D. Perform qualitative risk analysis.
Answer:

C

User Votes:
A
50%
B
50%
C
50%
D
50%

Explanation:
Risk management exercises—such as workshops, brainstorming, or facilitated sessions—are the
correct approach to proactively identify and address risks, especially early in the project. The
PMBOK® Guide states:
"Risk identification should be performed using systematic exercises and techniques such as
facilitated workshops, interviews, and checklists to ensure all potential risks are considered."
— PMBOK® Guide, 6th Edition, Section 11.2
Reference:
PMBOK® Guide, 6th Edition, Section 11.2

Discussions
vote your answer:
A
B
C
D
0 / 1000

Question 5

A financial service firm adheres to heavily regulated compliance legislation. During the firm's latest
project, the Chief Financial Officer (CFO) and the Chief Information Officer (CIO) endorsed a risk-
based approach. This approach ensured compliance with the legislative requirements for properly
storing confidential employee salary information. The risk manager recorded this information in the
project's risk management plan.
What is the organization's risk maturity level?

  • A. No maturity
  • B. Low maturity
  • C. Medium maturity
  • D. High maturity
Answer:

D

User Votes:
A
50%
B
50%
C
50%
D
50%

Explanation:
An organization that uses an integrated, risk-based approach supported by executive management
and documents this in a risk management plan demonstrates a high level of risk maturity. This aligns
with best practice models such as the PMI’s Organizational Project Management Maturity Model
(OPM3) and ISO 31000:
"High maturity organizations have risk management integrated with governance and strategic
decision-making, with executive-level endorsement and formal documentation."
— ISO 31000:2018, Section 5.2
"At the highest maturity, risk management is part of the culture and is proactively used to achieve
objectives."
— OPM3, PMI
Reference:
ISO 31000:2018, Section 5.2
PMI OPM3 Model

Discussions
vote your answer:
A
B
C
D
0 / 1000

Question 6

A risk manager is assigned to a mobile network deployment project with a strict contractually
agreed-on schedule. One of the key risks identified has materialized. There is insufficient staffing
because critical resources are dedicated to strategic projects in the organization. The risk manager
expected the resource manager to notice this, but the resource manager thought the project experts
would be alerting the team during the project.
What should the risk manager do to prevent this from happening again?

  • A. Document the risks and response actions in a clear manner.
  • B. Communicate with the project manager on the topic.
  • C. Assign owners who will be fully accountable to managing the risks.
  • D. Define the response plans and take the lead in implementing them.
Answer:

C

User Votes:
A
50%
B
50%
C
50%
D
50%

Explanation:
Assigning a risk owner is a foundational principle in risk management, ensuring that each risk has
someone fully accountable for monitoring, controlling, and responding to the risk. According to the
PMBOK® Guide:
"Risk owners should be assigned to each risk. The risk owner is the person responsible for planning
an appropriate risk response and ensuring it is implemented as planned."
— PMBOK® Guide, 6th Edition, Section 11.3.2.1
Without a clearly assigned risk owner, responsibility can be ambiguous, leading to gaps in monitoring
and response.
Reference:
PMBOK® Guide, 6th Edition, Section 11.3.2.1
Practice Standard for Project Risk Management, PMI, Section 5.3

Discussions
vote your answer:
A
B
C
D
0 / 1000

Question 7

A risk manager is integrated into a team overseeing a crucial software development project. During
the information gathering phase, the risk manager notices significant weaknesses in the maturity of
the risk management process. The team needs to establish a more structured approach to managing
risks, including the documentation of strategies, ownership structures, and details about the
organization's project risk baseline.
What should the risk manager do?

  • A. Prioritize the risk management plan.
  • B. Arrange the risk mitigation plan.
  • C. Create a risk action plan with risk owners.
  • D. Prioritize the risk register.
Answer:

A

User Votes:
A
50%
B
50%
C
50%
D
50%

Explanation:
A risk management plan is the foundational document for risk management. It defines processes,
ownership, strategies, and baselines, and must be developed first before other detailed risk actions.
PMBOK® Guide specifies:
"The risk management plan is the key document that outlines the approach, processes, roles,
responsibilities, and documentation requirements for risk management."
— PMBOK® Guide, 6th Edition, Section 11.1
Reference:
PMBOK® Guide, 6th Edition, Section 11.1

Discussions
vote your answer:
A
B
C
D
0 / 1000

Question 8

An organization is executing two projects — Project A and Project B — simultaneously. A previously
identified risk will impact the schedule for Project

  • A. Review the findings in Project A's closure documents and propose a new organizational process for portfolio risk management.
  • B. Consult with Project B's risk manager and determine where synergies might exist between the risk management plans for both projects.
  • C. Combine the risk registers for Project A and Project B and determine if there are any additional cross-project opportunities to exploit.
  • D. Continue executing the planned risk mitigation to avoid any additional schedule impact to Project A.
Answer:

B

User Votes:
A
50%
B
50%
C
50%
D
50%

Explanation:
Collaborating with other project risk managers ensures cross-project opportunities and risks are
leveraged or mitigated appropriately. The PMBOK® Guide encourages this approach:
"When risks or opportunities cross project boundaries, risk managers should consult with other
project teams to identify synergies and dependencies."
— PMBOK® Guide, 6th Edition, Section 11.1
Reference:
PMBOK® Guide, 6th Edition, Section 11.1

Discussions
vote your answer:
A
B
C
D
0 / 1000

Question 9

The sponsor of a construction project is upset about the results of the risk management team. The
sponsor believes the team did not properly identify the risks that could affect the project. The team
did manage the risks; however, some of the risk response strategies created secondary risks.
What should the risk management team have done to manage this situation?

  • A. Ensured to include the stakeholders in the team discussions
  • B. Encouraged involvement of the project team during the review meetings
  • C. Enhanced communication with the sponsor regarding secondary risk impact
  • D. Ensured the sponsor got more involved with the project risk planning
Answer:

C

User Votes:
A
50%
B
50%
C
50%
D
50%

Explanation:
Effective communication with sponsors and stakeholders about both primary and secondary risks is
crucial. PMBOK® Guide states:
"Secondary risks... should be communicated to stakeholders and sponsors to ensure transparency
and allow for appropriate responses."
— PMBOK® Guide, 6th Edition, Section 11.5
Reference:
PMBOK® Guide, 6th Edition, Section 11.5

Discussions
vote your answer:
A
B
C
D
0 / 1000

Question 10

During project execution for a software development program, a risk manager notices the results
vary from the stated expectations in the planning phase. The project team states that there was
unrealistic planning.
What should the risk manager do next to understand the differences between planning and
execution?

  • A. Engage with the team to present the actual results to the sponsor.
  • B. Prepare a management of change (MOC) to adjust the project cost and duration.
  • C. Move forward with the lessons learned from the sprint.
  • D. Review the assumptions to understand any change.
Answer:

D

User Votes:
A
50%
B
50%
C
50%
D
50%

Explanation:
Assumptions made during planning need to be reviewed to understand deviations in actual results.
PMBOK® Guide states:
"Reviewing project assumptions is key to understanding variances between planned and actual
performance, as invalid or changed assumptions often cause project deviations."
— PMBOK® Guide, 6th Edition, Section 11.2
Reference:
PMBOK® Guide, 6th Edition, Section 11.2

Discussions
vote your answer:
A
B
C
D
0 / 1000

Question 11

Some engineers are completing an activity that will alert the project team if there is a risk of
requiring additional effort to complete the project. What should the risk manager do in case the
trigger arises?

  • A. Activate the contingency plan.
  • B. Request a reserves increase.
  • C. Add the alert to the risk register.
  • D. Update the risk response plan.
Answer:

A

User Votes:
A
50%
B
50%
C
50%
D
50%

Explanation:
A contingency plan is pre-planned for specific risk triggers. When the trigger is observed, the
contingency plan should be activated as specified. PMBOK® Guide states:
"If a risk trigger occurs, the corresponding contingency plan or fallback plan should be implemented
as documented in the risk response plan."
— PMBOK® Guide, 6th Edition, Section 11.6
Reference:
PMBOK® Guide, 6th Edition, Section 11.6

Discussions
vote your answer:
A
B
C
D
0 / 1000

Question 12

A new project to develop a custom software solution for a high-profile client is being initiated. The
project sponsor emphasizes the importance of delivering the solution on time and within budget, as
this project could lead to significant future opportunities. The risk manager recognizes that the team
lacks a standardized approach to managing risks and that some team members are unfamiliar with
risk management practices.
What should the risk manager do?

  • A. Ask the sponsor to define the risk strategy to align with client needs.
  • B. Develop a framework and engage the team in creating a risk plan.
  • C. Train the team on basic techniques and defer the risk strategy for later.
  • D. Concentrate on high-priority risks to meet the sponsor's expectations.
Answer:

B

User Votes:
A
50%
B
50%
C
50%
D
50%

Explanation:
Establishing a risk management framework and involving the team in developing the risk plan
creates ownership and builds risk management capability. PMBOK® Guide states:
"A risk management plan should be developed early in the project and should involve the project
team to ensure buy-in and effective implementation."
— PMBOK® Guide, 6th Edition, Section 11.1
Reference:
PMBOK® Guide, 6th Edition, Section 11.1

Discussions
vote your answer:
A
B
C
D
0 / 1000

Question 13

A project team is overseeing the construction of a new office building. The project is complex,
involving multiple contractors, regulatory requirements, and a tight schedule. During a team
meeting, the risk manager realizes that a formal risk identification exercise has not yet been
conducted.
Given the project's complexity, what should the risk manager do?

  • A. Wait until halfway through the project to identify risks, as most issues will be clear by then.
  • B. Conduct the exercise with the key team members, excluding external stakeholders.
  • C. Facilitate a risk identification exercise with key stakeholders, considering all factors.
  • D. Focus only on identifying the most obvious risks to save time and project resources.
Answer:

C

User Votes:
A
50%
B
50%
C
50%
D
50%

Explanation:
For complex projects, facilitating a risk identification exercise with key stakeholders ensures
thoroughness. PMBOK® Guide recommends:
"Formal risk identification with all relevant stakeholders is critical, particularly in complex projects, to
ensure all potential risks are recognized."
— PMBOK® Guide, 6th Edition, Section 11.2
Reference:
PMBOK® Guide, 6th Edition, Section 11.2

Discussions
vote your answer:
A
B
C
D
0 / 1000

Question 14

A risk manager schedules workshops for identifying risks about an initiative involving multiple
business units, recruitments for different roles, procurements, technological uplift, training, and
changes in the ways of working. Who should participate in the risk management activity?

  • A. Core project team
  • B. Internal and external stakeholders
  • C. Key business stakeholders
  • D. Internal stakeholders only
Answer:

B

User Votes:
A
50%
B
50%
C
50%
D
50%

Explanation:
Including both internal and external stakeholders ensures diverse perspectives and comprehensive
risk identification. PMBOK® Guide states:
"Stakeholder participation, including both internal and external stakeholders, is essential during risk
identification to ensure a broad and complete identification of risks."
— PMBOK® Guide, 6th Edition, Section 11.2
Reference:
PMBOK® Guide, 6th Edition, Section 11.2

Discussions
vote your answer:
A
B
C
D
0 / 1000

Question 15

During a project team meeting, a risk manager realizes that the initial assumptions on the project
schedule are too optimistic. The risk manager believes that the project might not meet its deadline
as initially stated.
What is the reason for misunderstanding the assumptions from the beginning?

  • A. Government regulations have changed in the last week, and now additional approval processes are required.
  • B. The team's compensation was reduced and they lost the motivation to comply with the project deadline.
  • C. The stakeholders prepared the initial schedule assumptions based only on the results of the last project.
  • D. The sponsor had neither presented the actual results to the stakeholders nor updated the initial assumptions.
Answer:

C

User Votes:
A
50%
B
50%
C
50%
D
50%

Explanation:
Relying solely on historical project results for new assumptions can cause errors, as unique
circumstances may differ. The PMBOK® Guide notes:
"Assumptions should be validated as part of project planning. Overreliance on past project data
without proper contextual analysis can result in unrealistic expectations."
— PMBOK® Guide, 6th Edition, Section 11.2
Reference:
PMBOK® Guide, 6th Edition, Section 11.2

Discussions
vote your answer:
A
B
C
D
0 / 1000
To page 2