Questions for the CAPM were updated on : Dec 07 ,2025
Who identifies project requirements in the early phase of the project?
D
If the estimate at completion (EAC) is 25, and the budget at completion (BAC) is 17, what is the
variance at completion (VAC)?
A
A product owner asked for a change in one of the requirements during the elicitation phase. What
should the business analyst do?
B
Why is working in iterations usually more time consuming than using a predictive life cycle?
D
An adaptive project manager is told that a new industry regulation will affect an upcoming
deliverable. Where should this be recorded?
A
Which three processes are generally included in risk management? (Choose three)
B, C, D
A software project has completed the first iteration, and the testing manager noted that some
features were not incorporated and would not approve the software. The business unit manager who
will use the software is satisfied with the software and wants to start the rollout.
What should the project manager do?
B
The executive committee of a company is reviewing its portfolios. Which of the following would be
helpful to evaluate success?
D
An organization that is being interviewed online has recently experienced a severe network outage.
Consequently, the organization has stated that it is required to have a working data network.
Which classification should be assigned to data network requirements?
D
A project team is starting to work on a project based on a Kanban approach. In order to frame the
capacity of the team's workflow at any moment, the project manager will need to restrict the
maximum amount of activities to be performed.
Which element will the project manager handle?
C
A project's aim, from a business perspective, is moving an organization from one level to another to
achieve a specific objective. What is the goal for a project's successful completion?
B
Which of the following is provided by the critical path method?
C
An adaptive team's velocity dropped significantly in the last sprint due to the planned vacation of
two team members. The project sponsor wants to know how many more sprints it would take to
complete the remaining project.
How should the project manager calculate the anticipated velocity for future sprints?
C
Which two of the following can be used as communication tools between the business analyst and
the rest of the project team? (Choose two)
D, E
A new project was approved and the project manager is discussing the most suitable delivery
approach with the project sponsor. Which three of the following are characteristics of a traditional
project delivered using a linear delivery approach? (Choose three)
B, C, E